Deputy Minister of Engineering and Planning of Montazer Ghaem Power Plant, referring to the antiquity of Montazer Ghaem Power Plant, said: “Major repairs have been put on the agenda in different parts of the power plant, and such measures have progressed by 45% so far.”
Fazel Bakhshi, Deputy Minister of Engineering and Planning of Montazer Ghaem Power Plant, today in an interview with a Fars reporter in Karaj, said: RI repairs in the 4-gas unit of Shahid Montazer Ghaem Power Plant started on January 29 and have progressed more than 45% so far.
Montazer Ghaem Power Plant Engineering and Planning Deputy stated: The operations carried out in the mechanics department, including repairs in the combustion chamber, turbines, compressors, generators, valves and peripherals, are also underway.
He said: “Repairs of the electrical sector, including generators, transformers, electric motors, module switches, meters, protection relays, breakers, panels and دارد are also on the agenda.”
Deputy Minister of Engineering and Planning of Montazer Ghaem Power Plant stated: These repairs include control equipment of turbine coupe, loaded coupe, service and testing and calibration of control equipment, single cooling system equipment, gas charge system, generator cooling system, gas fuel system equipment In the panel will be ESDV and..
The official announced the overhaul of three steam units in the electrical and control sections and said: “This operation will be completed within the next 75 days.”